Project Info
Client
Saudi Aramco
Status
Completed
Location
Saudi Aramco
Contractor
Khoanini International Company
Project Value
SAR 1.2 Million
Project Duration
8 months
Completion Date
October 2025
Total Built-Up Area
5 kilometers
Project Overview
The Construction of Installation of fence was undertaken by El-Masa El Zahabia Contracting Company to deliver to Saudi Aramco. The steel fence installation project was executed to enhance perimeter security, control access, and protect critical Saudi Aramco assets. The scope included supply, fabrication, and installation of steel fencing in accordance with Saudi Aramco Engineering Standards (SAES) and project specifications. The work was completed under the supervision of the Project Management Team (PMT), with full coordination between construction, QA/QC, safety, and contractor teams.
Scope of Work
- Supply and installation of steel fence panels, posts, and gates
- Excavation and concrete foundation work for fence posts
- Anti-corrosion coating and painting
- Installation of barbed wire / razor wire (if applicable)
- Fabrication of custom gates and access points
- Removal of existing fencing (if required)
- As-built documentation and final inspection
Compliance with Saudi Aramco Standards
The project adhered to the following standards and procedures:
- SAES-L-350 – Fencing and Gates
- SAES-Q-006 – Construction Quality Requirements
- SAEP-122 – Project Documentation
- GI and SAF Series – Safety and Work Permit Requirements
- Aramco Material Specifications (SAMSS) for steel and coatings
All materials were inspected through MIRs, and installation activities were monitored through RFI submissions and PMT approvals.
Project Execution Performance
Quality Performance
- All materials met Aramco-approved vendor requirements
- Welds, coatings, and alignments passed QA/QC inspections
- RFIs were closed without major NCRs
- As-built drawings were submitted and approved
Schedule Performance
- Work progressed according to the approved schedule
- Minor delays occurred due to permit constraints and weather conditions
- Final completion achieved within acceptable project tolerance
Safety Performance
- Zero Lost Time Incidents (LTI)
- Daily toolbox talks and JSAs conducted
- All activities performed under valid work permits
- Proper barricading and housekeeping maintained throughout
Stakeholder Feedback
- PMT: Satisfied with quality and adherence to standards
- Safety Department: Noted strong compliance and proactive hazard control
- QA/QC: Appreciated timely inspections and documentation
- End User: Confirmed fence alignment and gate operation met operational needs
Conclusion
The steel fence installation project was completed successfully, meeting Saudi Aramco’s requirements for safety, quality, and schedule. The installed fence enhances site security and provides durable, long-term protection for Aramco facilities. The project team demonstrated strong coordination, compliance, and commitment to Aramco’s standards.